M2: Analysis of Comparable Project Planning/Management Offerings

M2 Product/Service Profile: WebProject

Date: 17 August 2000

Copyright (c) 2000 Frank Castellucci
All Rights Reserved

Associated project: Specification Writing for Web-based Project Planning Software

Project URL: http://sohodojo.com/techsig/project-planning-project.html

sXc Project detail: http://sourcexchange.com/ProjectDetail?projectID=24 (SourceXchange is out of business.)

Project coordination: Sohodojo

Sponsors: Position open

Sponsors (M1-3): Opendesk.com and Collab.Net

Core Team: Jim Salmons and Frank Castellucci

1 Overview

The intent of this document is to provide feedback from analysis of products that are comparable to the general goals of the project. The focus is on key technological areas with an overriding concern in regards to role collaboration capability.

2 Product/Service Profile [ All assessments, this topic ]

2.1 Name of offering

WebProject

2.2 Publisher/Author/Service-provider

Novient

2.3 URL for more information

http://www.wproj.com

2.4 Type - one or more of local client, client/server, web service, etc.

WebProject is a Three-Tiered (server, application server, client), multiuser, multi-project application written completely in Java. There are no plug-in requirements or other local configurations other than a Java VM and Java enabled browsers.

2.5 Pricing/Availability

A price/license schedule has been requested, but as yet I have not heard back from Novient.

2.6 Assessment based on hands-on experience or info-only?

Hands on in User, Team Member, Leader, and Administrator role. Did not participate in the setup and configuration of a WebProject server as for the test trial a system is pre-configure and hosted by the provider.

2.7 Reviewer comments

As a closed source system, WebProject can't be considered as a starting code base for open source initiatives.

3 System Constraints [ All assessments, this topic ]

3.1 Physical Limitations

Not applicable

3.2 Software Limitations (operating systems, plug-ins, drivers)

All of WebProject interactive modules are implemented as web pages or Java Server Pages (JSP), a Java Virtual Machine (JVM) is required.

3.3 Implementation Limitations (number of projects, tasks per projects, users, roles)

Resource restricted.

3.4 Does the software assume a specific project management methodology, if so which one(s)?

The documentation suggests a methodology (although not which) should be considered to enhance the quality of the project. The only area that enforces a methodology is in the Project Proposal feature, which potentially requires an acceptance sign off before a project can be created.

3.5 Reviewer Comments

As a closed source system, WebProject can't be considered as a starting code base for open source initiatives.

4 Collaboration [ All assessments, this topic ]

4.1 What is the interaction model? (Real-time dynamic views, publish/subscribe, email, user queries, etc.)

WebProject provides a plethora of collaboration facilities, including:

  1. E-mail
  2. Project Discussion boards
  3. Task level annotation and threaded discussions.
  4. Real time Chat
  5. Event notification via e-mail
  6. Reporting
  7. Voting

In addition, each project has a Web Page space for general presentation and limited support for content (documentation) management. Access to the various collaboration facilities can be controlled on an individual basis by Administrators and Leaders.

4.2 When used in project planning mode, is team communication supported?

WebProject offers multiple ways to collaborate from the Project Planning task perspectives, of these there are two (2) options specifically designed for issues support: Project Pinboards and Task Discussions, and Chatter.

Project Pinboards and Task Discussion

The two components are presented in a single dialog box with discussion topics presented in the top half, and the relevant messages around a discussion shown in a threaded view in the bottom half. Because the Gannt chart and Project Pinboard can be open at the same time, WebProject utilizes a model view controller (MVC) metaphor and will change the Project Pinboard context as you select different tasks in the Gantt chart.

Chatter

Chatter provides a virtual meeting room for real-time exchanges. Chatter sessions can be either Chaired or not, where chairing a meeting allows the Chairperson to determine which topics are to be discussed, and which chat members have the floor. Topics can be taken from the Project Pinboard, or defined at the time of chat. Discussions can be marked persistent which allows for later retrieval for continued discussions, or viewing by other users. There is no limit to the number of simultaneous Chatter sessions.

4.3 When used in project monitoring mode (more modest a target than project management), how is team member interaction handled? ('project-manager -centric' or peer interaction; is there an ad hoc issue management facility, etc.)

In addition to the e-mail and chatter facility WebProject provides two facilities that address higher level of collaboration focus: Project Message Boards and Web Boards.

Project Message Board

The Project Message board can be used to discuss higher level issues such as project issues and risks. Like the Task Discussions, message topics are threaded and presented in a tree view.

Web Board

Accessed through the documentation management facility, the Web Board is an enterprise wide discussion, information, issues, and news facility. The Web Board is implemented as part of the enterprise Web Page and Documentation structure.

4.4 What are the 'key indicators' used to keep project team members and stakeholders informed of the state of the project?

  1. Planned versus Actual hours reporting
  2. Availability versus Allocation reporting
  3. Budget versus Actual Cost reporting
  4. Full featured Gannt Chart (see 10.5 for details)

4.5 Does the product or services concurrency features facilitate or hinder team member collaboration?

WebProject appears to have addressed facilitating collaboration as a fundamental requirement of the system, to the point that collaboration is the focal point of most of the tools and facilities.

4.6 Security features

All users are required to login to the system for access, at which point the user profile accessibility controls are used to allow/deny access to various aspects of the project as defined by the Administrator. In addition, the tool implements a two phase commit model by which changes in the user space must be committed to the server to become part of the project.

4.7 Reviewer Comments

The developers of WebProject have provided a thought out collaboration model in relationship to project management and participation. This is a must have minimum example for anyone considering a serious Project Management development effort.

5 Role Support [ All assessments, this topic ]

A Role characterizes the system participants of in terms of responsibility. A role can be people or other systems. For example, a developer is a role that has different responsibility than a SQA tester. In this section, we will provide what provisions the system under review provides for describing the person/role, and what processing rules that it may imply.

5.1 What is the 'person/role' model?

WebProject predefines four (4) roles in the system:

  1. Administrators - All privileges of other user types Granted full access to both project data and project configuration, as well as creating new users.
  2. Leaders - Project managers or team leader access. Leaders are limited to manage users that meet Group and RBS codes that it has been granted authority over.
  3. Team Members - Can manipulate tasks that it is assigned, participate in discussions and chat, as well as configure it's own calendar.
  4. Users - Can be assigned to projects but cannot access the tools or projects themselves.

5.2 How are 'person/role' elements related to 'organization/group' elements?

When preparing the WebProject server for use, there are various configuration codes that are used to define organizational elements into the system, the three (3) primary codes are:

  1. Group Codes - Organizationally specific codes used to describe a particular department/group/team that is populated by a given resource.
  2. Resource Breakdown Structure (RBS) codes - A unique identifier given to each resource to define people (labor), materials, goods, CPU, etc.
  3. Types - defines a organizational type that can be used for filtering and reporting.

5.3 Can one person fill many roles? Can one role be filled by many persons? (resource/skill pools, etc.)

Yes, there are a number of ways this is supported:

  1. When creating the user profile, they can be marked as User, Team Member, Leader, or Administrator, which can be combined.
  2. Leaders can authorize a Team Member to be the leader of a summary task. A summary task is a composite of multiple tasks within its group.

5.4 Reviewer Comments

While I would have liked to see Role modeling, where the access levels of one 'role' can be extended and specialized, they have provided at least the flexibility of copying existing definitions, which reduces setup time.

6 Concurrency [ All assessments, this topic ]

Concurrency is defined by the implementations locking and transaction model. As such, the granularity of the locking will determine the liveliness of the system. The finer the granularity of locking, the more lively the interactions may be. Another aspect of concurrency is in regards to work-flow and the transaction model, does the system support "conversational or long-term transactions" for example.

Concurrency is defined by the implementations locking and transaction model. As such, the granularity of the locking will determine the liveliness of the system. The finer the granularity of locking, the more lively the interactions may be. Another aspect of concurrency is in regards to work-flow and the transaction model, does the system support "conversational or long-term transactions" for example.

6.1 Single or multi-user

WebProject puts a tremendous emphasis on multi-user, highly collaborative project management.

6.2 What is the implementation technology supporting concurrency?

Web server, Java Server Pages, and two-phase commit.

6.3 Revision Management

This is a manual effort facilitated by project archiving and download.

6.4 Reviewer Comments

7 Accessibility [ All assessments, this topic ]

In this section, we want to capture how accessible the system is from both a human interaction capability as well as support for the interchange of information from other systems.

7.1 Web-based

WebProject is enabled through HTML pages and Java Server Pages. Its general design assumes installation within an organizations intra-net.

7.2 Interchanges support (MS Project, XML, RDF, etc.)

Interchange occurs through the import and export facility.

7.3 Import/Export (MS Project, text, etc.)

WebProject can import and export from and to Microsoft Project Exchange (MPX) files, which are supported in a number of PC based project planning tools. In addition, WebProject supports archiving the project to a second database as well as saving the project as a template to be re-used to quickly setup new projects.

7.4 Mobile Users

Support not explicitly mention through hands-on or documentation.

7.5 Reviewer Comments

Working as designed.

8 Project Proposal Management [ All assessments, this topic ]

Is there a business processing rule that supports the tenet that before a project there is a proposal? If so, what are the processing rules that govern it's description and acceptance?

8.1 Vision/Goals specification

WebProject supports creating a project proposal which must be met with approval before the project plan for it can be opened.

8.2 Business Processing Rules

When preparing the WebProject server for use, the administrator configures the Project Approval list, which contains the e-mail address of all those who's approval is required to accept a proposal as a project. When a project proposal is made, the members of the list are notified by e-mail and they can then approve or reject a project proposal.

8.3 Implementation Specific Rules

There is no enforcement to configure an approval list. In this case, the user that makes the proposal can accept it automatically and create a project plan.

8.4 Reviewer Comments

This is really the only major nod to software development life cycle (SDLC) methodology that is included in WebProject.

9 Requirements Management [ All assessments, this topic ]

The tasks of creating a software system are usually (but not always) bound to initial requirements elucidated by analysis of the problem space. To what extent, if any, does the system under review support the requirement phase of the Software Development Life Cycle (SDLC)?

9.1 Documentation Controls

While WebProject provides documentation management for the web presentation of the company or project, it is not specific to managing Requirement Engineering documentation as there is no explicit function or methodology in the software.

9.2 Relationship to Task Management

Functionality does not exist.

9.3 Implementation Specific Rules

Functionality does not exist.

9.4 Business Processing Rules

Functionality does not exist.

9.5 Reviewer Comments

Nothing to comment on.

10 Task Management [ All assessments, this topic ]

10.1 What is the 'activity/task' model?

WebProject fully embraces the task model, including:

  • Summary Tasks and decompositional elements
  • Milestone designations
  • Multiple resource assignment
  • Critical / Non-Critical path
  • Task dependency constraints
  • Resource constraints

10.2 How are roles related to activity/tasks?

Leaders, or better, access is required to create tasks and assign resources. Team members maintain information on tasks assigned to them.

10.3 Is the product/service 'project-manager-centric' or can team members extend and/refine the plan within the realm of their own activity?

The full functionality of the Task Management facility is provided for Leaders and administrators. Team members can only modify those tasks assigned to the individual, and follow the methodology for extension through issue resolution.

10.4 Views: Predefined, user-configurable or both

All views, reports, and charts are pre-defined by WebProject. All users have configuration of preferences for content and layout, although the inclusion/exclusion of components is configuration controlled.

Preference Settings include:

  • Enable/Disable critical task paths in Gannt chart displays.
  • Enable/Disable tasks links in Gannt chart displays.
  • Enable/Disable resource assignment names in Gannt chart displays.
  • Auto-recalc and save every four (4) minutes in project plan maintenance.
  • Enable/Disable the display of project color code letters.
  • Locale/Language choices.
  • Date/Time format choices.

Administrator control specific to user access:

  • Limit projects that can be viewed using explicit project identifier, or project identifier masks.
  • Limit projects that can be edited using explicit project identifier, or project identifier masks.
  • Limit the outline nesting level that can be viewed.
  • Limit project plan view to just milestone indicators (tasks with zero duration).
  • Enable/Disable Project Pinboard and Project Discussion access.

Administrator control specific to view/report access:

  • Enable/Disable Project Reports
  • Enable/Disable Task Reports
  • Enable/Disable Assignment Reports
  • Enable/Disable Resource Pool Reports
  • Enable/Disable Cost in Reports
  • Enable/Disable Effort in Reports

10.5 Status reporting mechanisms (percent complete reports, 'flag-raising' or issue management features)

Status is reported for the individual as well as project managers through various views and reports. WebProject uses various icons to symbolize various type information (milestone, nested, detail, open, closed) as well as color codes for status.

Team Member Status Reporting

Upon signing on the system, team members can immediately access their tasks from a list of projects that they are an assigned resource to. Following are the views and controls where a member can immediately assess project status:

My Assignment

This display is presented in a mixed spreadsheet/tree view and is intended to give the user a started/completed birds-eye summary. Here you can see the list of tasks sorted by project, with start/finish dates per sizing analysis, as well as controls to indicate the activity has been started or completed. Changes made here are saved to the project database.

Assignment details

The details sheet is where the team member tracks the work effort associated with their assignments. Here you can specify actual hours worked, adjust the total units the task will take, indicate percent complete and remaining work units to complete the task. Changes made here are saved to the project database.

Gannt View

The Gannt view is a combination spreadsheet and Gannt chart of the project. Team members can modify aspects of the task (%complete, constraints, etc.) in the spreadsheet view and have it immediately reflected in the Gannt chart. This also allows multiple "what if" scenarios to be evaluated. Changes to the tasks are not saved to the database unless an explicit save operation is initiated.

This view may also show where there are issue discussions pending on a per task basis. See the Collaboration section (4) for more details.

Project Leader Status Reporting

Project Leaders have the same views as the team members, but it is obviously extended to include all of the resources of the project.

10.6 How are consumable/required task-specific resources handled?

Critical path and over-allocation reports, resource leveling, are all available to analyze and report problems before they happen.

10.7 Reviewer Comments

There is no doubt that the developers of WebProject placed as much emphasis on Project Planning/Task Management as they did on collaboration. At a minimum, any effort should consider this as an ideal model for Task Management.

11 Task Constraints [ All assessments, this topic ]

11.1 Task Dependency Internal (intra-project)

Tasks in WebProject support task and calendar constraints within the current project plan.

The task constraints are called predecessors and can be indicated as types Finish-Start (FS), Finish to Finish (FF), and Start-Start (SS). The types can be further refined using the standard lag (+) or lead (-) with a number of unit indicator. For example 1FS+2d describes a task that is constrained by the finish of task #1, and will lag start for 2 days once task #1 is completed.

Start No Earlier Than is a constraint that forces a tasks to start on or after the date indicated in the task description field.

11.2 Task Dependency External (inter-project)

Tasks can not reference other project plan tasks.

11.3 Resource constraints (expressed as percentage)

Resource constraints are supported in relationship to project calendars, task sizing and resource availability, all of which are fully configurable. Resource constraints include:

Calendars - Weekends, holidays, vacations, etc. can be marked as non-workable. These are considered in the Gannt View and overall project projections.

Availability - The amount of time percentage (0.0 - 1.0) per day a resource is available in a group or for assignment to a task. This constraint is considered in the reporting options for Leaders and Administrators to detect over allocation.

11.4 User defined constraints

Functionality not supported.

11.5 Reviewer Comments

For assessing critical paths, account/budget over-run tracking, resource leveling, and over-all capability, WebProject has done it right. The full feature/functionality set rivals that of the more familiar MS Project. Because of it's expressive richness in task details, it has the ability to interchange MS project content with it's own facility with no appreciable loss of important details.

12 Reporting [ All assessments, this topic ]

12.1 Pre-defined, user-defined or both

The following report categories and types are pre-defined by WebProject:

Project:

  • Project Overview
  • Project Detail
  • Project Pinboard
  • Project Discussion
  • Archived projects

Task:

  • Task Lists
  • Task Details
  • Task Discussions
  • Open Tasks

Resources:

  • Assignment reports
  • Assignment Details
  • Resource Assignments (Leaders/Admin only)
  • Resource Pool Reports (Leaders/Admin only)

12.2 Publisher-push by project manager or team member dynamic views?

Both are supported by WebProject.

12.3 Stakeholder-specific views?

Stakeholders as defined by the Role designation of the system. There is a catch-all Guest role, which allows more restrictive views (omissions of organizational sensitive information).

12.4 Multi-project analysis

The Executive Information System supports a high level view of all projects that the user has access too. From the main multi-project status display, individual projects can be drilled down to the task level. Access to details is limited to the profile that you are assigned as, with greater detail available to Leaders and Administrators.

12.5 What-if analysis

WebProject supports resource leveling and recalculation. Because of the two-phase commit model, multiple what-if analysis can be done without effecting the server side data.

12.6 Security features

Reports are limited by user profile settings and configuration by Administrators and Leaders.

12.7 Reviewer Comments

In addition to displaying real-time information from multiple aspects of the project, WebProject supports printing reports and saving to local CSV files. The lack of a query by form facility would have been nice as the WebProject development team may not have the domain expertise to provide enough reports to suit all potential users needs.

13 Multi-project Management [ All assessments, this topic ]

WebProject allows almost all elements of an existing project to templatized. This enable a high degree of re-use and time savings especially with multi-responsible teams and repetitive tasks structure.

13.1 Role Template library?

Users can be added to a resource pool. If there is a requirement that they have different access than their default profile, the administrator can assign which projects, by identifier, that they have additional capabilities on.

13.2 Repetitive Task library?

Project tasks can be saved to a Project template which allows re-use of the project structure (task elements, etc.).

13.3 Reviewer Comments

The ability to support multiple projects, templates, and task libraries is a must have for every serious open community, open source project management effort.

14 Post Mortem [ All assessments, this topic ]

It is often desirable to look back upon a completed project and enumerate what problems arose, the quality of how they were handled, and a gauge to the positive or negative effect on the baseline plan. This is primarily used as an quality accounting about the software development process.

14.1 Analysis and Reporting

WebProject supports the idea of post mortem analysis through continued collaboration and use of the annotation features (Project Pinboard, Project Discussion).

14.2 Is there an interface to a 'reputation-building' rating system for team members? If so, is there a 'disputed assessment' system to resolve conflicting opinions.

Functionality not supported.

14.3 Reviewer Comments

Nothing to comment on.

15 Subjective Impressions [ All assessments, this topic ]

15.1 User Interface: Strengths/Weaknesses

While I had some trouble getting the correct JVM mix on my machine, once that was done the product worked like a charm. I am convinced that if anyone is really serious about providing enterprise strength, distributed, culturally sensitive tools, than they must rely on and take advantage of client side processing with a minimal disruption to the user.

15.2 Project Modeling: Strengths/Weaknesses

From a full SDLC aspect, there was much to be desired in the lack of Role Modeling, Requirements Engineering, Implementation and Maintenance configuration management, and documentation/content management.

Clearly the muscle in this product is its painstaking detail to Collaboration and Project Planning.

15.3 Technology Platform: Strengths/Weaknesses

The use of Java shows a great strength in the project team at WebProject. It significantly reduces the installation and configuration nightmare when addressing a global, culturally diverse world.

15.4 Overall 'Wow' factor: 1 (low) to 5 (high)

SDLC = 1, Project Planning = 5, Project Management = 2, Product Development = 0, Product Maintenance = 0

15.5 Reviewer Comments

No comments.

DOCUMENT HISTORY

Version 0.9 - Draft
Version 1.0 - Final

### end of sxc24-m2-webproject-comparables.txt (Version 1.0) ###


© 1998-2010 Jim Salmons and Timlynn Babitsky for Sohodojo except as noted for project deliverable and working documents. Our Privacy Statement
"War College" of the Small Is Good Business Revolution
Website design and hosting by Sohodojo Business Services,
A Portfolio Life nanocorp

Support Sohodojo, the Entrepreneurial Free Agent and Dejobbed Small Business R&D Lab exploring Open Source technologies to support 'Small is Good' business webs for social/economic development
[ Support Sohodojo ] [ Translate page ]
[ Search site ]

Sohodojo home

About Sohodojo

BIG IDEAS for small business

TechSIG area


CCCT home

Community Collaboration Platform Project

OSS Project Planning Project


LegalSIG area

Nanocorp reading

Links/Resources

Donor/Sponsor Information


Go to the Visitor Center

 Go ahead, we can take it... Give us a piece of your mind. Complaint? Irritation? Suggestion?
Tell us, please.